For 40 working days, construction work was carried out on the construction of foundations in the production building.
Features of this project
Work was carried out on a construction assignment from equipment suppliers. Therefore, permanent geodetic and laboratory control was carried out at the facility. During the work, errors in the project documentation were identified and eliminated.Applicable equipment
In the performance of these works were used:
– Excavator.
– Dump truck.
– Set of equipment for general construction works: vibration seals, construction tours, equipment for diamond cutting of concrete, welding equipment, geodetic and laboratory equipment, excavator-loader, car concrete mixer, etc.Summary of Work Production
After mobilization at the construction site and installation of the construction module, surveyors began to work. During the first week, the PRP was developed. When dismantling and replacing the soil in the place of foundation installation, the remnants of concrete combat and construction debris were identified and disposed of. The foundation was made of sand with a layered seal and a chop. For the installation of formwork, reinforcement and embedded parts, the number of personnel was doubled. Layer-by-layer concrete foundations were carried out with constant support of geodetic and laboratory control. Special removal deserve anchor wells, which are made for hooked anchor bolts. Channels for engineering communications were covered with lids and painted. The final floor covering is made with a hardened layer to increase the service life. Executive documentation is provided for all the work done. All materials used have quality documents.Quality control of work
As part of quality control, daily construction control of works at the facility, incoming control of the structure, operational control and acceptance control, constant geodetic and laboratory control of the work performed were carried out.Possible and frequent mistakes
As practice shows, errors in construction always lead to an increase in the time and cost of work. To eliminate errors, the specialists of our company carry out construction control and document all violations. It is forbidden to use materials and products without quality documents. Before the start of work, it is necessary to conduct incoming control of project documentation.Used Normative and Technical Literature
SP 20.13330.2011 Loads and effects. Updated version of SNIP 2.01.07-85*;
GOST 21.101-97 SPDS. Basic requirements for project and working documentation.
SP 48.13330.2011 Construction Organization Updated edition of SNIP 12-01-2004Address: Moscow Region, Mytishchi, Passing Street
Start of work: August 2017.
End of work: October 2017.
Customer: TsOM MOST-1 LLC